Analysis of The Influence of Labor, Materials, and Site Characteristics on Individual Performance and Time Performance in The Implementation of Steel Frame Bridge Projects
DOI:
https://doi.org/10.59188/eduvest.v5i3.1796Keywords:
Labor, materials, characteristics of the place, individual performance, time performanceAbstract
Understanding the impact of project time performance on individual performance is key to demonstrating reliability, commitment, and valuable time management skills. This study aims to To find out, obtain, and analyze the influence of labor, material and site characteristics on individual performance of steel bridge construction projects, find out get, and analyze the influence of labor on Individual performance, find out get, and analyze the influence of material on Individual performance, find out get, and analyze the influence of site characteristics on Individual performance, find out, obtain, and analyze the influence of individual performance on time performance. find out, obtain, and analyze the control of labor factors, site characteristics, and materials on individual performance and time performance of steel bridge construction projects.
The type of research used is quantitative research, with a sample size of 100 people consisting of contractors, consultants and suppliers, with regression analysis assisted by spss 21 software and path analysis with SmartPLS 4 software.
The results of the study of labor, materials, and characteristics of the place together have a significant effect on individual performance in bridge construction projects, labor has a positive and significant effect on individual performance in bridge construction projects, materials have a positive and significant effect on individual performance in bridge construction projects, characteristics of the place have a positive and significant effect on individual performance in bridge construction projects, individual performance has a positive and significant effect on time performance in bridge construction projects and Control of labor factors.
References
Apriani, W., Suryanita, R., & Lubis, F. (2020). Evaluasi Kinerja Struktur Jembatan Pelengkung akibat Beban Gempa dengan Analisis Riwayat Waktu. Jurnal Infrastruktur, 6(2), 151-156.
Arumningsih. (2012). Perencanaan Dan Estimasi Biaya Pada Proyek Pembangunan Jembatan Patihan Kabupaten Sragen. Jurnal Teknik Sipil dan Arsitektur, 12(16).
Bakhtiyar, A., Soehardjono, A., & Hasyim, M. H. (2012). Analisis faktor-faktor yang mempengaruhi keterlambatan proyek konstruksi pembangunan gedung di kota lamongan. Rekayasa Sipil, 6(1), 55-66.
Bansambua, E. M. (2019). Faktor-Faktor yang Menyebabkan Keterlambatan Waktu Pelaksanaan Proyek pada Pekerjaan Jalan dan Jembatan di Kabupaten Morowali. Jurnal Maroso, 1(01).
Dharmawan, R. D., Safarizki, H. A., & Firdausi, A. A. Evaluasi Efektivitas Keputusan Addendum Proyek Terhadap Waktu Pekerjaan Proyek Berbasis Earned Value Method. J@ ti Undip: Jurnal Teknik Industri, 18(1), 51-61.
Enrico, Y., & Sumarman, S. (2020). Manajemen Konstruksi pada proyek pembangunan Jembatan untuk akses ke lokasi PT. Pertamina MB-04. Jurnal Konstruksi dan Infrastruktur, 8(1).
Ervianto, W. I., & MT, I. (2006). Studi Implementasi Teknologi Beton Pracetak Bagi Bangunan Gedung. In National Conference on Prospected Technology.
Gellysa Urva, & Aminah, S. (2022). Implementasi Metode Analytic Hierarchy Process dalam Pemilihan Proyek Kontruksi. JURNAL UNITEK, 15(2), 141-150. https://doi.org/10.52072/unitek.v15i2.405
Ginting, R., Purba, C. E., & Sinulingga, H. P. (2023). Analisa Manajemen Konstruksi Bangunan Bawah Pada Proyek Pembangunan Jembatan Overpass Ruas Kisaran-Indrapura STA 132+ 023. JURNAL Ilmiah Teknik Sipil, 12(2), 291-296.
Haseli, B., & Hasan Ebdali, E. (2022). Ranking of Project Delay Factors in the Construction of Civil Infrastructure, Case study: Tehran Highway Bridge. New Approaches in Civil Engineering, 5(4), 1-13.
Hai Nguyen, L. (2020). Empirical analysis of a management function’s failures in construction project delay. Journal of Open Innovation: Technology, Market, and Complexity, 6(2), 26.
Hair, J. F., Babin, B. J., Anderson, R. E., & Black, W. C. (2022). Multivariate data analysis (8th ed.). London, United Kingdom: Cengage Learning.
Hidayat, A., & Suripto, H. (2019). Klasifikasi Pengendalian Material dalam Mencegah Keterlambatan Proyek di Kabupaten Rokan Hulu. Aptek, 91-96.
Hudoyo, C. P., Rustendi, I., Sismiani, A., & Sunarwono, B. E. (2023). Evaluasi Kinerja Biaya dan Waktu Proyek Konstruksi Jalan dan Jembatan Kawasan Industri Terpadu (KIT) Batang dengan Metode Earned Value. Proceedings Series on Physical & Formal Sciences, 6, 42-47.
Husen, A. (2019). Manajemen Proyek (revisied). Yogyakarta: Cv. Andi Offset.
Intan, S. K., Muhyi, A., & Tengku, N. M. (2018). Alternatif Percepatan Waktu Dengan Penerapan Metode Time Cost Trade Off Pada Proyek Pembangunan Jembatan (Studi Kasus: Proyek Pekerjaan Jembatan Rangka Baja Namploh Kec. Samalanga Kab. Bireuen, Aceh). Portal: Jurnal Teknik Sipil, 10(2), 19-27.
Johari, S., & Jha, K. N. (2020). Interrelationship among belief, intention, attitude, behavior, and performance of construction workers. Journal of management in engineering, 36(6), 04020081.
Kala Kamdjoug, J. R. (2023). Change management and digital transformation project success in SMEs located in the Democratic Republic of the Congo. Journal of Enterprise Information Management.
Karthic, Prabakara, Sindhu Vaardini and A. Aswin bharath. Maximizing Real-Time Monitoring For Effective Delay Analysis In Bridge Construction Projects With Evm Scheduling. International Journal of Scientific Research in Engineering and Management (IJSREM). 8(1), DOI: 10.55041/IJSREM27859
Kuswandari, A. D., Koesmargoro, A., & Ervianto, W. I. (2018). Pengaruh Dampak Contract Change Order Terhadap Kinerja Kontraktor Proyek Studi Kasus: Rehabilitasi Jembatan Ngablak. Jurnal Teknik Sipil, 14(4), 255-282.
Larsen, K. R., Michie, S., Hekler, E. B., Gibson, B., Spruijt-Metz, D., Ahern, D., ... & Yi, J. (2017). Behavior change interventions: the potential of ontologies for advancing science and practice. Journal of behavioral medicine, 40, 6-22.
Mahapatni, I. A. P. S., Putra, C., & Murwanta, K. E. (2022). Analisis Kinerja Waktu dan Biaya Pelaksanaan Proyek dengan Metode Earned Value Pada Proyek Pembangunan Jembatan Pangkung Dalem Ruas Jalan Gitgit-Wanagiri. Jurnal Ilmiah Kurva Teknik, 11(2), 17-25.
Maulina, F., & Mahmuddin, M. (2020). Identifikasi Risiko Pada Proyek Pembangunan Penggantian Jembatan Baja Di Aceh Jaya Dan Aceh Besar. Journal of The Civil Engineering Student, 2(3), 211-217.
Nasution, W. S. I. (2012). Hotel Forest di Bukit Lawang Tema Green Architecture (Doctoral dissertation).
Ramadhan, F. (2021). Evaluasi Penjadwalan Kurva–S Dan Critical Path Method (Cpm) Dalam Mengendalikan Pelaksanaan Pondasi Bore Pile (Studi Pada Pekerjaan Jembatan di Jalan Relokasi Bendungan Tapin) (Doctoral dissertation, Universitas Islam Kalimantan MAB).
Rebut, R., Mangare, J. B., & Walangitan, D. R. (2018). Analisis Perbandingan Tenaga Kerja Lokal Dan Tenaga Kerja Luar Dalam Jasa Konstruksi Di Manado (Studi Kasus: Transmart). Jurnal Sipil Statik, 6(3).
Robbins, Stephen. 2019. Perilaku Organisasi. Edisi Kesepuluh. Jakarta; Indeks.
Sari, A. M. (2021). Faktor Yang Berhubungan Dengan Program Penanggulangan Covid-19 Pada Proyek Jembatan Ploso Jombang Menggunakan Analisis Fishbone. Jurnal Indonesia Sosial Teknologi, 2(09), 1460-1474.
Sianipar, H. B. (2013). Analisis Faktor-Faktor Penyebab Keterlambatan Penyelesaian Proyek Konstruksi Pengaruhnya Terhadap Biaya.
Sigit, A., & Nurhidayat, H. (2019). Penerapan Earned Value Concept pada Proyek Penggantian Jembatan Ruas Nanga Tepuai–Nanga Semangut Kalimantan Barat. Jurnal Teknisia, 24(2).
Simanjuntak, I. J., Siagian, R. T., Prasetyo, R., Rozak, N. F., & Purba, H. H. (2022). Manajemen Risiko Pada Proyek Konstruksi Jembatan: Kajian Literatur Sistematis. Jurnal Teknologi dan Manajemen, 20(1), 59-76.
Soeharto, I. (2001). Manajemen proyek dari konseptual sampai operasional. Jakarta; Erlangga
Sugiono, G. J., Antonio, J. K., & Ratnawidjaja, S. (2022). Analisis Faktor-Faktor Yang Mempengaruhi Cost Overrun Dan Pengaruhnya Terhadap Keuangan Proyek Konstruksi Di Surabaya. Jurnal Dimensi Pratama Teknik Sipil, 11(2), 76-83.
Sugiyono (2019). Metode Penelitian Kunatitatif Kualitatif dan R&D. Bandung: Alfabeta.
Surachmad, N., Azis, S., & Putranto, E. H. D. (2018). Faktor-Faktor Risiko Kegagalan Pencapaian Sasaran Proyek Tepat Waktu Dan Mutu Pada Pembangunan Proyek Jembatan Di Kabupaten Probolinggo. Infomanpro, 7(1), 1-12.
Tabrani, N., Mulia, A. P., & Anas, R. (2023). Analisis Faktor Keterlambatan Pelaksanaan Proyek Jembatan di Provinsi Sumatera Utara. Jurnal Syntax Transformation, 4(1), 119-133.
Trauner, T. J. (2019). Construction delays: Understanding them clearly, analyzing them correctly. Butterworth-Heinemann.
Tristania, A., & Nursin, A. (2019). Tinjauan Pengendalian Waktu Pekerjaan Jembatan Anak CBL Pada Proyek Jalan Tol Cibitung–Cilincing Seksi II. In Prosiding Seminar Nasional Teknik Sipil (Vol. 1, No. 1, pp. 639-647).
Wahyuningtyas, A., & Waskito, J. P. H. (2021). Analisa faktor faktor penyebab keterlambatan proyek pembangunan jembatan joyoboyo. axial: jurnal rekayasa dan manajemen konstruksi, 9(2), 071-078.
Widayat, W. W. (2019). Pengantar Manajemen Proyek & Ekonomi Teknik. Jakarta: Jurusan Tektik SIPIL UI
Wirabakti, D. M., Abdullah, R., & Maddeppungeng, A. (2017). Studi Faktor-Faktor Penyebab Keterlambatan Proyek Konstruksi Bangunan Gedung. Konstruksia, 6(1).
Published
How to Cite
Issue
Section
License
Copyright (c) 2025 Aries Andry Afriady, Agus Suroso

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.